North B - Sonoma Highway 101 Airport Interchange

Description: In Windsor, between Fulton Road and Windsor River Road. Replace the existing Airport Boulevard Overcrossing. Construct soundwalls in Windsor.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma
City Windsor
Zip Code
 
Senate District
02
Assembly District 01
Congressional District 06
 
Caltrans District
04
 
 
County/State Route Sonoma 101
Postmile Begin/End 25 29.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1711.0    1711  
Peak Period Time Savings (minutes)  102654.0    102654  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Sonoma County Transportation Agency Betcy Joseph (510) 286-5097   betcy.joseph@dot.ca.gov
Design (PS&E) Phase
Sonoma County Transportation Agency Betcy Joseph (510) 286-5097   betcy.joseph@dot.ca.gov
Right of Way Phase
CalTrans Betcy Joseph (510) 286-5097   betcy.joseph@dot.ca.gov
Construction Phase
CaTrans Betcy Joseph (510) 286-5097   betcy.joseph@dot.ca.gov
 
Corridor System Management Plan
CalTrans Betcy Joseph (510) 286-5097   betcy.joseph@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$22,242 $0 $22,242
SLPP
$1,866 $1,827 $3,693
Non-bond Funding
Local**
$21,700 $4,725 $26,425
Non Budgeted ETC
$0 $0 $0
 
Total**** $45,808 $6,552 $52,360

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$790 $-267 $523 $523
Design(PS&E)
$4,130 $2,393 $6,523 $6,523
Right of Way
$6,388 $613 $7,001 $0
Construction
$34,500 $3,813 $38,313 $36,206
 
Total* $45,808 $6,552 $52,360 $43,251

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2003 

06/15/2010 
 

 
04/01/2003 

06/15/2010 
100  03/01/2009 

06/30/2010 
-72 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2009 

09/30/2011 
 

 
09/01/2009 

03/01/2012 
100  05/01/2009 

02/29/2012 


Begin Right of Way Phase

End Right of Way Phase
06/15/2010 

09/30/2011 
 

 
06/15/2010 

03/01/2012 
95  10/01/2009 

 


Begin Construction Phase

End Construction Phase
12/31/2011 

12/31/2013 
 

 
10/01/2012 

10/01/2012 
08/08/2012 

06/30/2014 


-21 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/01/2015 
 

 
11/01/2014 

11/01/2015 
06/30/2014 

06/30/2016 


-8 
Corridor System Management Plan
Adoption Date 12/01/2010       
Implementation Date 12/01/2010       
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1711.0 1711
Peak Period Time Savings (minutes) 102654.0 102654

Bond Funding Cost
Adopted:
$24,108,000
Current Approved:
$22,242,000
Actual Expenditures:
$22,051,000

 

Status as of December 31, 2023.